Step 1 of 38 · Foundations
Leading work with uncertain outcomes
ML work can fail after a perfect effort. Your plans, status reports and definition of progress have to allow for that.
In software you can usually estimate the work because you know it can be built. With a learned model you do not know whether the target is reachable until you try. A team can do everything right and still miss.
Plan in bets, not tasks. Each bet has a question, a time box, a result that would make you stop and a result that would make you invest more. Report progress as what you learned and what you now believe, not as tasks closed.
The common mistake is to run model work on a feature schedule, then explain the slip as bad luck every sprint.
Try this week
- Rewrite your current top project as three bets, each with a question, a time box and a stop condition.
- Change one status update from tasks closed to what you learned and what you will do next because of it.
Signs you've got it
- Your plans name the result that would make you stop, and you have stopped at least one project because of it.
- Stakeholders can repeat your confidence level for each bet without you in the room.
Resources
- paperHidden Technical Debt in Machine Learning Systems (opens in a new tab)D. Sculley and colleagues
- bookFrom Models to Systems (Machine Learning in Production) (opens in a new tab)Christian Kästner
- videoLecture 1: Course Vision and When to Use ML (opens in a new tab)Full Stack Deep Learning
- articleThe New Business of AI (and How It's Different From Traditional Software) (opens in a new tab)Martin Casado and Matt Bornstein