Communicating status
Lead with the conclusion, state your confidence, and send it before anyone has to ask.
Engineers explain in order: what we tried, what we found, and finally where we are. Stakeholders read the first two lines. Put the conclusion there: on track or not, what changed, what you need.
A written weekly update saves hours of meetings. Keep the same structure each time so readers know where to look: status against the goal, what shipped, risks, asks. State your confidence in plain words and say what would change it.
Be careful with green. A project reported green for weeks that turns red overnight destroys trust in every later report. Amber with a reason shows control, not weakness.
Adjust depth to the reader. Your manager wants risks. A partner team wants dates and interfaces. Executives want the decision you need from them.
Try this week
- Rewrite your last status message so the first sentence is the conclusion and the second is the ask.
- Start a weekly written update on your team's main work and send it four weeks running.
Signs you've got it
- Stakeholders stop asking for ad hoc updates because yours answer their questions.
- Your status moves from green to amber before it moves to red.
Go deeper
What it looks like
Picture your team three weeks into a data migration that has been reported green from the start. On Monday, testing reveals a schema mismatch that could add two weeks. Your old update would open with the testing work and end with the risk.
This week the first line reads: amber, the migration date is at risk by up to two weeks because testing found a schema mismatch. The second line: you need the data team to confirm the field mapping by Wednesday. Below that, in the same order as every week, come what shipped, the risks and your confidence. You state it plainly: medium, back to high if the mapping is confirmed by Wednesday.
Your manager replies with a question about customer impact. The data team lead answers the ask directly. Nobody books a meeting. The next week you report green with the reason, and readers believe it because they watched it move through amber first.
Weekly status update template
[Project]: Green / Amber / Red
Headline: the conclusion in one sentence. On track or not, and what changed since last week.
Ask: the decision or help you need, from whom, by when. Write none if there is none.
Shipped this week
- ...
Risks
- The risk, its impact if it happens, and what you are doing about it.
Confidence: high, medium or low, and what would change it.
Next week
- ...
Keep the structure the same every week. Move to amber as soon as you have a reason. Write for the reader who stops after two lines.
Where it goes wrong
- Opening with what the team tried and burying the status. Put the conclusion and the ask in the first two lines.
- Keeping a project green to avoid a hard conversation. Move to amber with a reason as soon as you have one.
- Sending everyone the same detail. Give your manager risks, partner teams dates and interfaces, and executives the decision you need.
Resources
- articleSending weekly 5-15 updates (opens in a new tab)Will Larson
- articleHow to present to executives (opens in a new tab)Will Larson
- articleWeek in Review Leadership Comms (opens in a new tab)Lara Hogan
- articleUndervalued Software Engineering Skills: Writing Well (opens in a new tab)Gergely Orosz