Step 18 of 36 · Delivery
The first slipped deadline
The slip is yours now. Say it early, bring options, and cut scope before you add people or hours.
Do first: Planning and estimates
When a date slips, it is no longer the project's problem for you to comment on. It is yours, including the parts you could not control.
Say it as soon as you believe it, not when you are certain. Stakeholders forgive a slip they heard about a month ahead. They do not forgive one they discovered. Hoping the team will catch up is the usual reason for silence.
Arrive with options, not an apology: what ships on the date with less scope, what the full scope costs in time, and what you recommend. Cutting scope is the first tool. Adding people late slows the work, and asking for heroics spends trust you will need later.
Never name the engineer whose task ran over. Upward, the miss is yours.
Try this week
- For your riskiest commitment, write down what you would cut first if it slipped by two weeks.
- Tell one stakeholder about a risk before it becomes a delay, with the trigger that would confirm it.
- Question the status item you trust least until you could explain it to someone else.
Signs you've got it
- Stakeholders hear about schedule risk from you first, with options attached.
- After a slip, the team reviews what happened and changes one planning habit.
Go deeper
What it looks like
Say three weeks before a launch you come to believe the data migration will be at least two weeks late. You are not certain yet. You message the product lead and your manager that day and book thirty minutes. You open: "The migration is at risk of slipping by two to three weeks. I want to give you options now rather than a surprise later."
You present three: ship on the date without historical data and backfill afterwards; ship the full scope two weeks late; or move an engineer off a lower-priority project, which delays that project by a month. You recommend the first.
The product lead asks whose task ran over. You say: "That's on me. I'll show you what we're changing in how we plan." After launch the team reviews what happened and adds a migration spike to future estimates.
Raising a slip early
Subject: [Project] date at risk, options inside
- What's at risk: [deliverable] on [date] is likely to slip by [range].
- Why: [one or two causes, no names].
- Options:
- Ship on [date] with [reduced scope].
- Ship the full scope on [later date].
- [Other trade-off] at the cost of [what].
- My recommendation: option ___, because ___.
- What I need from you: a decision by [date].
- What would confirm or clear the risk: [trigger] by [date].
Where it goes wrong
- Waiting until you are sure the date will slip. Raise it as soon as you believe it, with the trigger that would confirm it.
- Adding people late to catch up. Cut scope first, because new people slow the work in its final weeks.
- Naming the engineer whose task ran over. Own the miss upward, then fix the planning habit with the team.
Resources
- bookShape Up: Decide When to Stop (opens in a new tab)Ryan Singer
- articleThe Twinge (opens in a new tab)Michael Lopp
- articleAn epic treatise on scheduling, bug tracking, and triage (opens in a new tab)Avery Pennarun
- articleBreaking Down Tasks (opens in a new tab)Jacob Kaplan-Moss