Step 16 of 36 · Delivery
Planning and estimates
A plan is a statement of capacity and risk. Estimate in ranges and say what would change them.
As an engineer you estimated your own tasks. Now you commit for a team, to people who will build their own plans on your word.
Start from capacity, not from the wish list. Subtract holidays, on-call, support and interviews before you fit any project in. New managers plan as if every engineer codes every day, then spend the quarter explaining.
Give estimates as ranges and say what drives the width. Two to five weeks, wide because nobody has touched the billing code, is more useful than three weeks. Ask what decision the estimate is for. If none depends on it, a rough size is enough.
Let the people doing the work estimate it. Your own number reflects how long it would have taken you, uninterrupted, a year ago.
Try this week
- Work out your team's real capacity for next month after leave, on-call and support, and compare it with the plan.
- Restate your largest current estimate as a range and list the two unknowns that drive it.
Signs you've got it
- Your plans include slack, and nobody is surprised when it gets used.
- Stakeholders ask what would narrow the range, not why you cannot commit to a date.
Go deeper
What it looks like
Say you are asked to commit to next quarter's plan. Your team has five engineers and the wish list holds eight projects. You start with capacity: one person is on leave for a month, on-call takes one person each week, and support and interviews take a day a week from two others. What is left is well short of five full-time engineers.
You ask the engineers to estimate the top projects as ranges. The billing rework comes back as four to nine weeks, wide because nobody has worked in that code. You ask the product lead what decision depends on it. She needs to know whether it lands before a pricing change.
You commit to three projects, show the billing work as a range, and add a two-week spike at the start to narrow it. When the spike ends, you send the product lead an updated range.
Capacity worksheet
- Engineers multiplied by working weeks in the period: ___ person-weeks
- Minus leave and public holidays: ___
- Minus on-call and support: ___
- Minus interviews, onboarding and meetings: ___
- Available for projects: ___
- Hold back some slack for the unexpected: ___
For each project, one line: "We expect [project] to take [low] to [high] weeks. The range is wide because [unknown]. We'll know more after [spike or milestone] on [date]."
Where it goes wrong
- Planning as if everyone codes every day. Subtract leave, on-call, support and interviews before fitting any project in.
- Giving a single number. Give a range and name what drives its width.
- Estimating on the team's behalf. Let the people doing the work estimate, then question their assumptions rather than their number.
Resources
- articlePurpose Of Estimation (opens in a new tab)Martin Fowler
- articleSoftware Estimation Is Hard. Do It Anyway. (opens in a new tab)Jacob Kaplan-Moss
- articleEvidence Based Scheduling (opens in a new tab)Joel Spolsky
- bookShape Up: Stop Running in Circles and Ship Work that Matters (opens in a new tab)Ryan Singer
- articleYes, You Should Estimate Software Projects (opens in a new tab)Gergely Orosz