Agile practices that do and do not transfer
Short feedback loops and visible work transfer to hardware. Sprints that each end in a shippable product do not.
Much of agile transfers if you take the intent and leave the ritual. Short feedback loops, small batches, visible work, frequent integration and regular retrospectives all help a hardware team. Firmware can and should run with continuous integration and automated tests.
What does not transfer is the idea that every two weeks ends with a shippable increment, or that scope can flex freely while the date holds. A mould cannot be delivered in slices. Dates are set by lead times and gates.
So shorten the loops you control. Use simulation, printed parts, development kits and breadboards to answer questions before the expensive build. Let the cost of change, not doctrine, decide how much to design up front.
Try this week
- Pick one open design question and find the cheapest experiment that answers it before the next build.
- Hold a retrospective after your next build with all disciplines and the factory contact in the room.
Signs you've got it
- Risky questions are answered with cheap prototypes weeks before the build that depends on them.
- The team plans in short cycles, and the plan is anchored to build dates and gates.
Resources
- articleYes, Hardware Can Be Agile! (opens in a new tab)Nancy Van Schooenderwoert
- articleSix Myths of Product Development (opens in a new tab)Stefan Thomke and Donald Reinertsen
- articleThe New New Product Development Game (opens in a new tab)Hirotaka Takeuchi and Ikujiro Nonaka
- bookTest-Driven Development for Embedded C (opens in a new tab)James Grenning
Talks to watch
- 52 minUncompromised Agile is Safer and Better for Regulated Medical Products (DDD Europe) (YouTube, opens in a new tab)Nancy Van Schooenderwoert
- 44 minThe Big Ideas Behind Lean Product Development (Lean Startup Conference 2013) (YouTube, opens in a new tab)Don Reinertsen