Cost of change over time
The price of a change rises in steps at each commitment. Know the steps and decide what must be right before each one.
In hardware the cost of a change does not rise smoothly. It jumps at commitments: schematic release, tooling order, certification test, first production lot, shipment. A resistor value is free on Monday and costs a board respin on Friday.
Most of a product's lifetime cost is fixed by early design choices, long before most of the money is spent. That is why early phases deserve your best people and real review time, even when little seems to be happening.
Use this to sequence decisions. Decide late what stays cheap to change, usually firmware and configuration. Decide early, and with evidence, what is about to be cut in steel. Keep a list of frozen items and require a written change request to reopen one.
Try this week
- Draw your project timeline and mark each commitment point with what a change costs before and after it.
- Introduce a one-page change request for anything already frozen: reason, cost, schedule effect, approver.
Signs you've got it
- Design questions get settled before the commitment they affect, not in the week after.
- Late change requests arrive with a cost and schedule estimate attached.
Resources
- guideNASA Systems Engineering Handbook: 2.5 Cost Effectiveness Considerations (opens in a new tab)NASA
- articleSix Myths of Product Development (opens in a new tab)Stefan Thomke and Donald Reinertsen
- paperBest Practices: Capturing Design and Manufacturing Knowledge Early Improves Acquisition Outcomes (opens in a new tab)U.S. Government Accountability Office
- articleThe Second Toyota Paradox: How Delaying Decisions Can Make Better Cars Faster (opens in a new tab)Allen Ward and colleagues