Step 12 of 36 · Delivery
Long-lead items and schedule risk
Parts, tools and lab slots with long lead times set your critical path. Order early at risk and manage each risk by name.
Your schedule is set by the slowest thing you wait for: a custom display, an injection mould, a certification lab slot, a chip on allocation. These long-lead items define the critical path. Engineering effort elsewhere cannot shorten it.
Know the lead time of every critical part and tool, and the date each order must go out. You will often order before the design is proven. That is a bet, so make it deliberately: what does it cost if the design changes, and what does it cost to wait?
Keep a short risk list with an owner, a trigger date and a fallback for each item: a second source, an alternative part, a parallel design path. Hold schedule margin openly and do not let it be negotiated away.
Try this week
- List the ten longest-lead items in your product with order dates. Mark those that must be ordered before validation.
- For your top three schedule risks, write the trigger date and the fallback you would switch to.
Signs you've got it
- You place at-risk orders knowingly, with the cost of being wrong written down.
- A schedule risk has been retired by a fallback you prepared in advance.
Resources
- guideNASA Systems Engineering Handbook: 6.4 Technical Risk Management (opens in a new tab)NASA
- guideGAO Schedule Assessment Guide: Best Practices for Project Schedules (opens in a new tab)U.S. Government Accountability Office
- articleThe Bullwhip Effect in Supply Chains (opens in a new tab)Hau Lee, V. Padmanabhan and Seungjin Whang
- articlePerforming a Project Premortem (opens in a new tab)Gary Klein