Step 31 of 36 · Manufacturing and field · checkpoint
Checkpoint: ready to ship in volume?
A self-assessment before the ramp. Every no you ship with is a problem you have chosen to meet in the field.
Before you approve the ramp, answer these with your leads. Ask for evidence, not confidence.
- Has every requirement been verified on units built with production parts, tools and processes?
- Are the required reliability and certification results in hand?
- Does production test cover every customer function, with yield at target over a full run?
- Is every critical part available for the forecast, with a plan for the single-sourced ones?
- Can you update firmware in the field and recover from a failed update?
- Is there a named owner for returns, security reports and sustaining work?
A no is not always a stop. It is a risk someone must accept in writing, with a date to close it.
Try this week
- Answer the six questions separately from your quality and operations leads, then compare and discuss differences.
- Turn each no into a dated item with an owner, and record who accepted the risk of shipping with it open.
Signs you've got it
- The ramp decision is recorded with the open risks and the name of the person who accepted each.
- Engineering, quality and operations give the same answers to these questions.
Resources
- guideProduct Realization: companion resources, templates and checklists (opens in a new tab)Anna C. Thornton
- paperBest Practices: DOD Can Achieve Better Outcomes by Standardizing the Way Manufacturing Risks Are Managed (opens in a new tab)U.S. Government Accountability Office
- guideNASA Systems Engineering Handbook: 5.5 Product Transition (opens in a new tab)NASA